> For the complete documentation index, see [llms.txt](https://docs.dietrichs.com/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://docs.dietrichs.com/tutorials/tutorials-en/creating-from-dietrichs/delivery-journey/design-to-manufacture/2.-understanding-mos-the-organizational-backbone.md).

# 2. Understanding MOS: The Organizational Backbone

MOS stands for **Model, Organization, Structure**. It's Dietrich's system for organizing thousands of components across multiple dimensions. Think of it as a filing system for your building components.

#### Why MOS Matters

Without MOS:

* You can't efficiently filter components
* You can't organize outputs by supplier or phase
* You can't generate targeted material lists
* You can't track what goes where

With MOS:

* ✓ Filter by supplier with one click
* ✓ Generate material lists for specific packages
* ✓ Export machine files for specific work orders
* ✓ Track components through manufacturing and installation

***

#### MOS Default Settings

By Default the program organizes materials into some pre-configured MOS sets.  A MOS set is created for every floor or roof in the model. Materials created in that floor are added to that MOS set. &#x20;

#### The Key MOS Structures

Dietrich's offers multiple MOS types under option  6.  Here are the essential ones:

**1. Group MOS(Numerical Identifiers). Option 6-6.**&#x20;

**What they are:** Positive or negative integers you assign to components\
**How they work:** Completely flexible - you define what the numbers mean

**Common uses:**

* **By supplier:** -1 = Supplier A, -2 = Supplier B, -3 = Supplier C
* **By phase:** 1 = Phase 1, 2 = Phase 2, 3 = Phase 3
* **By type:** 10 = Beams, 20 = Columns, 30 = Panels

**Example from our expert Jens:**

> "We organize everything by supplier. MOS Group -1 is all the components going to our main CNC supplier, -2 is the glulam manufacturer, -3 is hand-cut components. This way I can filter and export everything for each supplier separately."

***

**2. Building MOS**

**What they are:** Vertical levels of your building\
**How they work:** Automatic assignment when you create components in Floor Plan, Wall Design, etc.

**Standard hierarchy:**

* Foundation
* Floor 1
* Floor 2
* Floor 3
* Roof

**Use this for:**

* Organizing by construction phase
* Filtering what you're working on
* Separating deliveries by floor

***

**3. Packages vs. Elements: THE CRITICAL DISTINCTION**

**This is the most important concept in MOS, and the most commonly confused.**

From Dietrich's V22.01 official documentation:

> **Packages:** "grouped by process step: Machine, delivery ... / **is not assembled from individual parts** / often overlapping for several walls, ceilings ...."

> **Elements:** "assembled from individual parts / position of individual part important, element plan / **assembly before delivery to construction site** / part of a wall, ceiling, roof surface"

Let's break this down clearly:

***

#### PACKAGES: Process Organization

**Definition:**\
A grouping of components for a MANUFACTURING or LOGISTICS purpose. Components in a package remain as individual pieces - they are NOT assembled together.

**Think of a package as:** A shipping container, work order, or delivery batch

**Characteristics:**

* Grouped by how they're made or delivered
* Components stay separate
* Can contain parts from multiple walls, floors, or roofs
* Used for manufacturing planning and logistics

**Examples:**

* **Package: "CNC-Batch-Tuesday"**\
  Contains 240 studs that will all be machined together on Tuesday's CNC run. These studs will later go into 15 different wall panels.
* **Package: "Delivery-Floor2"**\
  All Floor 2 components that fit on one truck. Includes beams, panels, and connectors from different elements.
* **Package: "Supplier-A-Glulam"**\
  All glulam beams being fabricated by Supplier A, regardless of which building or floor they go in.

**When to use packages:**

* Organizing CNC machine runs
* Planning truck deliveries
* Coordinating supplier orders
* Tracking manufacturing batches

***

#### ELEMENTS: Product Organization

**Definition:**\
A group of components that ARE physically assembled together into a unit BEFORE delivery to the construction site. Used for installation planning.

**Think of an element as:** A prefabricated panel or pre-built assembly

**Characteristics:**

* Components are assembled together
* Position of each part matters (assembly drawing needed)
* Delivered as ONE complete unit
* Installed as a single piece (one crane lift)

**Examples:**

* **Element: "Wall-Panel-W201"**\
  Assembled in shop from: top plate, bottom plate, 12 studs, sheathing, window frame. Arrives at site as one complete wall panel.
* **Element: "Floor-Cassette-F105"**\
  Pre-assembled floor section with: 8 joists, blocking, and decking. Delivered as complete unit, installed with one crane lift.
* **Element: "Truss-T14"**\
  Assembled truss with: top chord, bottom chord, 6 web members, gusset plates. Complete structural unit.

**When to use elements:**

* Pre-fabricating wall panels
* Creating floor cassettes
* Building trusses
* Planning crane lifts (one element = one lift)
* Organizing installation sequence

***

#### The Dual Assignment: Why Components Can Belong to BOTH \*\*\*

**From V22.01 documentation:**

> "**Objects must be able to belong to an element and a package.** Therefore, the elements and packages have now become separate structures..."

**What this means:**\
A single component can (and often should) be assigned to BOTH a package AND an element simultaneously. They serve different purposes at different stages of the workflow.

**Example: The Journey of a Stud**

```
Component: Stud S-042 (2x6 SPF, 8' long)

PACKAGE: "Supplier-B-CNC-Tuesday"
↓ Purpose: Manufacturing & Delivery
↓ Goes to Supplier B for CNC machining on Tuesday
↓ Machined together with 239 other studs
↓ Delivered as individual piece

ELEMENT: "Wall-Panel-W201"
↓ Purpose: Assembly & Installation  
↓ Assembled into wall panel in staging area
↓ Position: 4th stud from left, 16" o.c.
↓ Installed as part of complete wall panel
```

**Both assignments exist at the same time!** The package tells us how it gets made and delivered. The element tells us what it gets built into and how it's installed.

***

#### Visual Comparison: Package vs. Element

```
┌─────────────────────────────────────────────┐
│             PACKAGE                         │
│  "CNC-Batch-Tuesday-Supplier-B"            │
│                                             │
│  Contains (as separate pieces):             │
│   • Stud S-001 → will go in Wall W-201     │
│   • Stud S-002 → will go in Wall W-201     │
│   • Stud S-003 → will go in Wall W-202     │
│   • Stud S-004 → will go in Wall W-202     │
│   • ... 236 more studs ...                 │
│                                             │
│  ✓ Machined together                       │
│  ✓ Delivered on same truck                 │
│  ✗ NOT assembled together                  │
│  ✗ Installed separately in different walls │
└─────────────────────────────────────────────┘

┌─────────────────────────────────────────────┐
│             ELEMENT                         │
│  "Wall-Panel-W201"                          │
│                                             │
│  Contains (assembled together):             │
│   • Top plate (from Package A)             │
│   • Bottom plate (from Package A)           │
│   • Stud S-001 (from Package B)            │
│   • Stud S-002 (from Package B)            │
│   • ... 10 more studs (from Package B)     │
│   • Sheathing (from Package C)             │
│   • Window frame (from Package D)           │
│                                             │
│  ✓ Pre-assembled in staging area           │
│  ✓ Delivered as ONE unit                   │
│  ✓ Position of each part critical          │
│  ✓ Installed as single piece               │
└─────────────────────────────────────────────┘
```

***

#### Quick Decision Guide: Package, Element, or Both?

| Your Situation    | Package? | Element? | Why?                                                          |
| ----------------- | -------- | -------- | ------------------------------------------------------------- |
| Prefab wall panel | ✓ Yes    | ✓ Yes    | Parts machined separately (Package), then assembled (Element) |
| Large glulam beam | ✓ Yes    | ✗ No     | Manufactured and delivered (Package), but installed as-is     |
| Individual studs  | ✓ Yes    | ✗ No     | Machined in batch (Package), installed individually           |
| Complex truss     | ✓ Yes    | ✓ Yes    | Parts from multiple suppliers (Packages), assembled (Element) |

***

**4. Buildings, Rooms, Free MOS (Brief Overview)**

**Buildings:**\
Separate multiple structures in one project file (e.g., Building A, Building B, Amenity Center)

**Rooms:**\
Organize by interior space (useful for residential, renovation work)

**Free MOS:**\
Create your own custom categories for project-specific needs

**Note:** These are less commonly used than Groups, Storeys, Packages, and Elements. Don't feel you need to use them unless you have a specific need.

***

#### Complete MOS Hierarchy Diagram

```
PROJECT
├── Building 1
│   ├── Storey: Foundation
│   ├── Storey: Floor 1
│   │   ├── MOS Groups: -1 (Supplier A), -2 (Supplier B), -3 (Supplier C)
│   │   ├── Packages: CNC-Batch-A, Delivery-Tuesday, Hand-Cut-Beams
│   │   └── Elements: Wall-W201, Wall-W202, Floor-F105
│   ├── Storey: Floor 2
│   │   └── [similar structure]
│   └── Storey: Roof
│       └── [similar structure]
└── Building 2
    └── [similar structure]
```

***

#### Real Example: How our Expert  Use MOS

**Expert's Approach (Design-Outsource Model):**

"For every project, I know upfront who the suppliers will be. So I set up my MOS groups by supplier:

* MOS Group -1: Main CNC supplier (Hundegger Robot)
* MOS Group -2: Glulam manufacturer
* MOS Group -3: Hand-cut components
* MOS Group -4: Steel fabricator

Then I organize everything into packages:

* Package: 'Supplier-A-CNC-Floor1'
* Package: 'Supplier-A-CNC-Floor2'
* Package: 'Supplier-B-Glulam'
* Package: 'Supplier-C-HandCut'

This way, I can filter everything for each supplier with one click, export their machine files, generate their material lists, and create their 2D drawings. It's simple and it works."

**Key insight:** It's not essential to  use complex ERP systems. He uses MOS groups, packages, spreadsheets, and PDFs. That's it.

***

**End of Part 1: Foundation**

You now understand:

* ✓ The two business models
* ✓ MOS and why it matters
* ✓ The critical difference between Packages and Elements
* ✓ How real practitioners use MOS